Usually projects culminate to careful and pedantic installation. Our installation and assembling teams have gained their strong experience for example in underground installations down to 500 meters, pipe installations and assembling in factories and mines.
Filling stations need to fulfil very demanding environmental permit requirements, so we do our installations with extreme exactness. We also double check always, that the products haven’t been damaged for example in transporting.
When needed, we can carry out installations very quickly. This has also been proved; UniContain team has the world record in the fastest filling station installation:

1. Saturday 6.00 PM – Earthworks start
2. Sunday 10.54 AM – Installation starts
3. Monday 04.30 PM – Finishing
4. Tuesday 4.00 PM – Ready station in use